Build Series: Mission Hills Shopping Center

Building Retail Excellence: Mission Hills Shopping Center Takes Shape
BUILD Series
October 13, 2025
Build Series: Mission Hills Shopping Center
Build Series: Mission Hills Shopping Center
No items found.
No items found.
No items found.
No items found.
No items found.
No items found.
No items found.
No items found.

April 22, 2026

Construction at Mission Hills Shopping Center continues toadvance as façade improvements move forward across multiple areas of theproperty. Framing and roofing are now complete at the NE Shops, SE Vons Corner,and Sherwin-Williams storefront, with plaster installation underway as newexterior finishes begin to define the updated look.

With these milestones in place, the transformation of theshopping center is becoming increasingly visible. The shift from the originalmansard-style façade to a modern, boxed-out design is now clearly taking shapeacross the plaza.

This includes the completed sitework such as new landscape,planters, drive aisle, and trash enclosure which have already added value tothe Von’s and Ace Hardware anchor stores. These overall site improvements havealso provided a plaza wide foundational for a newly upcoming Raising Canes,which will easily integrate with the newly completed and ongoingconstruction.  

Throughout construction, the shopping center has remainedfully operational. Temporary signage, designated pedestrian pathways, andprotected walkways ensure safe and seamless access for customers, while trafficcontrol measures maintain clear separation between construction activities andpublic circulation. These coordinated efforts allow the project to progressefficiently while minimizing disruption to tenants and daily operations.

DesignCollaboration Driving Value

During façade redevelopment, the team identified a designchallenge related to framing requirements for the new gable vent features,which initially introduced significant cost impacts. Through closecollaboration between Bergman and MMA Architecture, an alternative solution wasdeveloped that preserved the architectural intent while reducing structuralcomplexity. This value engineering effort resulted in approximately 80% costsavings—delivering meaningful value without compromising design.

Main Vons Façade – Strategic Resequencing

Work at the main Vons façade has been temporarily deferred toaccommodate a redesign effort. To maintain overall momentum, the schedule wasproactively sequenced, allowing crews to shift focus to other active areas. Asa result, progress continues without impact to the overall project timeline.

What’sNext?

Plaster installation will continue across active zones,followed by preparation for final finishes and architectural detailing. Asadditional areas undergo transformation, the full vision of the shoppingcenter’s modernization continues to come to life.

We look forward to sharing continued progress as MissionHills Shopping Center evolves into its new identity.

No items found.

February 11, 2026

As the new year begins, construction at Mission Hills Shopping Center has moved from site improvements into the next visible phase of transformation. With plaza upgrades now complete, crews have started demolition of the existing façade skin, removing plaster and roofing materials as part of the shift from the original mansard profile to a new, modern boxed-out design.

Scaffolding is now erected in key areas, allowing work to progress safely and efficiently as the center’s updated architectural identity begins to take shape.

Because tenants remain open and operating, maintaining safe and intuitive access for customers continues to guide every step of the process. Temporary signage has been installed throughout the property, clearly directing visitors along designated pathways. Pedestrian tunnels are in place where overhead work occurs, and traffic control measures help separate construction operations from public circulation.

These protections allow renovation work to advance while businesses maintain normal daily activity.

The team also navigated challenging weather conditions following a late-December storm. By proactively securing completed work and executing rapid dewatering procedures, crews were able to quickly return to operations once conditions improved. As a result, the project remains on schedule with no impact to upcoming milestones.

Looking ahead, façade reframing will continue as we build the structure that will support new architectural finishes and design elements. Each step brings the shopping center closer to a refreshed, contemporary appearance that will serve tenants and the community for years to come.

We look forward to sharing further progress as the transformation continues.

No items found.

December 30, 2025

Since our October update, work at Mission Hills Shopping Center has progressed into the final phase of site improvements. This portion of the renovation includes building the new trash enclosure, installing an underground sewer line, upgrading existing light pole heads to energy-efficient LED fixtures, and adding multiple new planter areas throughout the plaza.

In close coordination with the City of Los Angeles Public Works team, several key inspections were successfully completed, allowing us to open the new drive aisle ahead of schedule. Thanks to this collaboration, we were able to finish all work in front of Vons before their holiday shutdown, helping ensure shoppers experienced minimal disruption during the busiest time of the year.

Looking ahead, major site activities are expected to wrap up by early January. From there, the plaza-wide façade renovation will begin, starting with demolition at the main Vons entry. Scaffolding and pedestrian tunnels will be set in place so foot traffic can safely continue and all stores remain open while construction transitions into this next phase.

No items found.

October 13, 2025

Here at Bergman, we’re proud to have over 30 years of great testimony in each sector we’ve served, including that of retail and retail development. Our passion for delivering excellent results in each project has proved true in past ventures, such as the Crossroads Shopping Center in Bellevue, Washington and the expansive 50-acre Lake Elsinore Marketplace, demonstrating our leadership and expertise in this sector.

We’ve recently begun construction on a new project within a shopping center owned by Balboa Retail Partners, a real estate investment company dedicated to pursuing retail opportunities nationwide through in-house leasing, redevelopment and management. Our team, including Regional Director Ed Romero, Senior Project Manager Jacob Santoyo, Project Manager Larry Gore, and Superintendent Tomas Hogan, is improving one of their properties, the Mission Hills Shopping Center, located at the intersection of Sepulveda Boulevard and Devonshire Street in Mission Hills, California. Our goal is to aid in the company’s mission to pursue retail opportunities nationwide.

Site work began in September after a brief delay. The scope of this project consists of modernization of the plaza wide façade and site remodel of the existing 81,904 square foot space— notably the four buildings located in the shopping center. The façade remodel will include new roof tower elements and a new boxed out design with stucco, metal slats, and hard board finishes.

Our team is currently in phase one, kicking off site work with a demo of the existing planters and city sidewalk. We have since then relocated a light pole while building new planters and a drive entrance. The full scope of phase one also includes a re-slurry and re-strip of the existing asphalt.

As construction progresses, we look forward to helping Balboa Retail Partners further their mission of creating vibrant, high-performing retail destinations. This project not only reflects our dedication to quality and innovation but also reinforces our commitment to delivering projects to the highest standards. Stay tuned for continued updates as we bring this vision to life.

No items found.

Related Insights