

September 29, 2026
September brought another exciting month of progress at Fellowship Baptist Church as construction continued to move from structural work and building systems toward the architectural finishes that will define the completed project. With multiple trades working throughout the campus, the transformation is becoming increasingly visible, both inside the existing church and across the new addition.
One of the most noticeable changes this month has been the progress on the building's exterior. Installation of the Exterior Insulation and Finish System (EIFS) is underway, giving the new addition its architectural character and bringing the design closer to the original vision. Exterior stone veneer installation has also begun, introducing a complementary finish that will enhance the church's updated appearance. With the combination of stone, EIFS, and expansive storefront openings, the new entrance is beginning to take on the welcoming presence envisioned for the congregation and surrounding community.
Inside the existing church, significant progress was made on the first-floor renovations, including restrooms and other remodeled spaces. Drywall installation continued throughout these areas, while electrical rough-in was completed and HVAC rough-in advanced. Fire alarm installation is now getting underway, marking another important step toward completing the building's essential systems. The new stairways have also been installed, establishing the connections between the renovated areas and improving circulation throughout the facility.
The new foyer continued to advance as well, with mechanical systems and interior construction progressing alongside exterior work. Roofing materials were lifted into place in preparation for the next phase of roof installation. Meanwhile, rough grading around the addition was completed, bringing the surrounding site closer to its final elevations and preparing the way for future site improvements and landscaping.
Another major highlight this month was the progress at the church's Activity Center. Originally an additional scope of work beyond the main expansion, Bergman worked closely with Fellowship Baptist Church to help coordinate the design and secure the necessary permits to move this portion of the project forward. The existing multipurpose building is now undergoing renovations that will provide updated spaces primarily focused on the church's youth ministry, while remaining available for the entire congregation.
The Activity Center will feature a multipurpose recreational court designed to accommodate basketball, volleyball, and pickleball, creating opportunities for recreation, fellowship, and community engagement. Additional improvements to the existing building will help transform it into a more functional and welcoming environment for church activities and events. This added scope represents an exciting extension of the overall project and reflects the collaborative relationship between Bergman and the church as its vision continues to develop.
As construction moves into October, attention will remain focused on advancing exterior finishes, roofing, interior drywall and finishes, mechanical and electrical installations, and continued improvements at the Activity Center. With the building envelope taking shape and the renovated interior spaces beginning to resemble their final layouts, the project is entering a particularly rewarding stage of construction.
From the foundations and structural steel installed earlier this summer to the architectural finishes now transforming the exterior, each month has brought Fellowship Baptist Church closer to its vision. September was especially significant because the transformation is no longer limited to the new addition. The entire campus is beginning to evolve, creating spaces that will support worship, fellowship, youth activities, and community outreach for generations to come.
August 25, 2026
Construction continues to take shape at Fellowship Baptist Church as the project transitions from major structural work into building enclosure, interior build-out, and MEP rough-in.
Throughout August, significant progress was made on the new addition as roofing, exterior framing, and DensGlass sheathing helped bring the building closer to being fully dried in. With the structure increasingly protected from the elements, crews are now able to push forward with more interior work.
Inside the existing church, MEP rough-ins advanced enough for insulation and drywall to move forward, creating a noticeable transformation from the exposed framing and utilities seen earlier in construction. Second-floor metal stud framing was also completed, defining the new rooms and circulation areas as MEP work continues throughout the space.
The new two-story foyer is also beginning to take shape, with HVAC ductwork roughed in and insulated throughout the new structure. As these overhead systems progress, the coordination behind the future architectural ceilings and gathering spaces is becoming increasingly visible.
With the project moving from foundations and structural steel toward enclosed and finished spaces, the vision for the Fellowship Baptist Church expansion is becoming clearer each week. Heading into September, the team will continue advancing the building envelope, second-floor MEP rough-ins, drywall, exterior façade, ceilings, and interior finishes.
July 25, 2026
The Fellowship Baptist Church Expansion continued to make remarkable progress throughout July, bringing the vision for the new facility into sharper focus. What began as structural framing has quickly transformed into a recognizable building, with the new entrance and gathering spaces now taking shape and showcasing the future home for worship, fellowship, and ministry.
One of the project's biggest milestones this month was reaching approximately 98% completion of the structural steel framework, while nearly 90% of the structural steel roof decking has also been installed. With the building's structure nearly complete, crews are preparing to transition into the next phase by drying in the building and advancing exterior systems.
Inside the new addition, construction activity has accelerated as interior metal stud framing reached roughly 85% completion. At the same time, mechanical, electrical, and plumbing rough-ins continue throughout the facility, laying the groundwork for future classrooms, gathering spaces, offices, and ministry areas. Installation of new HVAC equipment is also progressing, with careful coordination to keep the existing sanctuary systems operational until the new equipment is ready for commissioning.
Work within the existing church has also reached an important milestone. The second-floor demolition is now complete, and new wall openings have been finalized to seamlessly connect the expansion with the existing facility. Structural lintels have been installed over each opening, creating the framework that will ultimately unify the two buildings into one cohesive campus.
Another exciting achievement this month was the approval of permits for the Legacy Center renovation, allowing the next phase of improvements to move forward alongside the expansion. Together, these projects represent a significant investment in creating modern, functional spaces that will serve Fellowship Baptist Church and the Durham community for years to come.
Looking ahead to August, crews will complete the remaining structural steel, continue roofing and exterior wall installation to dry in the building, advance mechanical, electrical, and plumbing rough-ins, and begin preparing areas for drywall and interior finishes. With each milestone reached, the vision for Fellowship Baptist Church moves one step closer to becoming a reality.
June 29, 2026
Construction at Fellowship Baptist Church made significant strides throughout June as the project advanced from foundational work into vertical construction. With each milestone completed, the vision for the church's expansion is becoming more tangible.
Early in the month, crews completed foundation work and placed the slab-on-grade for the new addition. Shortly thereafter, structural steel began rising, defining the footprint of the future two-story entrance and gathering space. Seeing the building's framework take shape marked an exciting turning point, giving church members and the project team their first glimpse of the new front entrance that will welcome generations to come.
Inside the existing facility, progress continued just as steadily. Interior demolition moved forward to prepare for the renovation, allowing crews to install underground plumbing, relocate utilities, and complete structural shoring for the new openings that will connect the existing sanctuary with the expanded lobby. These behind-the-scenes improvements are critical to creating a seamless transition between the church's historic structure and its modern addition.
Looking ahead to July, construction will continue with additional structural steel, roof framing, masonry, exterior wall systems, and ongoing mechanical, electrical, and plumbing rough-ins. Each phase brings Fellowship Baptist Church one step closer to delivering a revitalized campus that honors its longstanding history while creating a welcoming environment for worship, fellowship, and community for years to come.
Stay tuned as we continue sharing the progress of this exciting transformation.
May 20, 2026
Construction is officially underway on the transformation and expansion of Fellowship Baptist Church, a project designed to modernize the church’s front-facing experience while enhancing accessibility, circulation, and community gathering spaces. The project includes a new two-story lobby addition, expanded restrooms, updated fellowship and coffee areas, ADA-compliant circulation improvements, and renovations to the existing front areas of the church. Exterior upgrades will introduce refreshed architectural elements, new glazing, roofing systems, and enhanced signage to create a more welcoming presence for both the congregation and the surrounding community.
Currently, construction activities are in full progress with demolition approximately 50% complete. The team has completed the building pad and is actively working through underground plumbing, electrical panel relocation, and structural footer installations for the new column systems. Upcoming milestones include concrete footers, CMU wall construction, slab placement, continued demolition activities, and anticipated structural steel delivery in mid-June.
One of the project’s most unique design elements is the integration of the church’s existing brick exterior wall into the new foyer space, preserving the history and character of the original structure while blending it with modern architectural features. Additional highlights include cloud acoustical ceiling panels, expansive glazing systems, and open gathering spaces designed to create a warm and inviting environment for fellowship and community engagement.
Located adjacent to a major freeway, the church’s highly visible location makes this project especially impactful for the surrounding Durham community. As the first major renovation and expansion since the church’s original construction in the early 1970s, the project represents a significant investment in the future of the congregation and its outreach efforts for years to come.